Why a Pier Came Out at Ancich Waterfront Park Before the Fishing Dock Goes In

October 22, 2026

"We are the only place that I know on the West Coast of North America that has a significant fleet that relies on private property for moorage," Guy Hoppen, executive director of the Gig Harbor Boatshop and a commercial fisherman, told Future Tides this February.

That quote explains the cranes on the south shore this fall. The City of Gig Harbor is building the Commercial Fishing Homeport at Ancich Waterfront Park. It will be a public dock for working fishing boats, the first of its kind in a harbor whose fleet has gotten by on a handful of family-owned piers. If you've walked Harborview Drive since September, you've watched the project begin by removing a pier. Federal permits required the habitat repairs to come first.

The order of work on the south shore

The U.S. Army Corps of Engineers required the city to finish the mitigation work before building any part of the homeport marina. That one rule set the order you've seen from the sidewalk.

  1. Maritime Pier, next to Tides Tavern. From about Sept. 8, the city closed several parking stalls and the through-access in the Maritime Pier lot so crews could install a larger stormwater outfall. In its newsletter, as The News Tribune reported, the city said the old outfall was undersized and "has caused erosion on the surrounding beach, making the beach unstable and unsuitable for aquatic life." Redside Construction bid $231,000 before sales tax for this piece. By the city's Oct. 7 update, the new outfall was in and crews were finishing the beach restoration.
  2. Jerkovich Pier, at Ancich Waterfront Park. Crews started removing the old pier on Sept. 14, and the city now lists that removal as complete. National Fisherman described the pier as aging, with creosote and other environmental concerns.
  3. Utilities under the existing Ancich Pier. This work was scheduled to start the week of Oct. 12 and take a few weeks. The city says the park and the pier stay open to the public during this stage, and it will post notice of any temporary closure.
  4. The new floats. National Fisherman reported that if the schedule holds, contractors should finish in-water construction by Feb. 15, 2027, before the state's seasonal fish window closes.

In her email to The News Tribune, Gig Harbor Senior Engineer Stephanie Seibel explained why the steps fit together this way. The outfall replacement and the removal of the old dock "are both mitigation projects that will be completed before the new construction begins on the Homeport." The city is also buying credits through the Puget Sound Partnership. Together, the projects and credits fully replace the marine habitat the new dock affects, which the state calls "no net loss." The Maritime Pier outfall started as a separate project. The city realized it could count that work toward the homeport's mitigation.

Why the boats have been tied up somewhere else

Ancich Waterfront Park is an old fishing site. In a 2023 history of the park's net shed, Gig Harbor Now reported that Mateo Petrich's net shed, which stood on a wharf, was built there between 1888 and 1891. Nick Castelan built his net shed on the park's eastern lot in 1901, and the article identifies the Jerkovich family as his descendants. Peter Ancich bought the neighboring Lots 6 and 7 in 1917.

The net sheds still line the harbor today. Future Tides notes that most now serve as homes, restaurants and a museum. Few are still places where working crews repair and replace purse-seine nets. Fishermen who have lived in Gig Harbor for decades often keep their boats in Seattle, Anacortes, Bellingham or even Astoria, Oregon.

Gregg Lovrovich is president of the Gig Harbor Commercial Fishermen's Club. His family's net shed, dating to the early 1900s, sits between the Gig Harbor Boatshop and the Harbor History Museum. "There's fishermen that are in Seattle, that live in Federal Way, or in Poulsbo and would much rather keep their boat here, rather than drive the traffic to Seattle all the time," he told Future Tides. "We're just trying to keep it so there's a presence of fishing boats in Gig Harbor." His club has promised $200,000 toward the dock.

The city bought the Ancich waterfront property in 2012, and the homeport plan followed. That puts the dock well over a decade in the making before the Notice to Proceed went out on Sept. 8, 2026. On Aug. 22, the Skansie Netshed Foundation marked 150 years of Gig Harbor's commercial fleet with "Fishermen Feed the World" at Skansie Brothers Park, with net-mending demonstrations and current and former fishermen on hand. City staff came to answer questions about the homeport.

What is settled, and what is still a proposal

The dock's size and contract are settled. How it will run has not been finalized. Here's where each piece stands as of the city's October update and the summer coverage.

Item Status Detail
Capacity Planned Up to 17 commercial fishing vessels
Vessel size Reported two ways About 58 feet per Future Tides; roughly 60 to 70 feet per National Fisherman
Construction contract Approved Aug. 10, 2026 Redside Construction, roughly $3.6 million
Total project cost Reported Aug. 2026 About $4.9 million, including mitigation credits and earlier expenses
Monthly moorage rate Staff proposal, July 2026 $10 per square foot of vessel length
Who can tie up Staff proposal, July 2026 Commercial fishing vessels only, no transient moorage
Public access Staff proposal, July 2026 Open 9 a.m. to 5 p.m. daily
Opening Expected 2027 In-water work due by Feb. 15, 2027; ribbon-cutting expected in spring 2027

The cost figures cover different scopes. The city's capital project page still lists a $3.48 million budget for design, permitting and construction. The News Tribune's roughly $4.9 million total adds a $480,000 Puget Sound Partnership payment and just over $370,000 in earlier expenses. At a July 16 council meeting, staff had shown a worst-case estimate of up to $5.2 million. Public Works Director Jeff Langhelm said he would be surprised if bids came in that high, and the awarded bid landed near $3.6 million.

The access rules are the ones neighbors will feel most. According to National Fisherman, staff tied the commercial-only proposal to the project's current permits and to concerns from neighboring property owners. Staff described the dock as both "a working waterfront and an educational destination," open to the public during daytime hours. That would make it a place to watch working boats at the dock, a short walk from the Boatshop and the museum. Staff estimated the proposed rate would bring in about $121,000 a year against just over $54,000 in yearly operating and maintenance costs.

The rest of Harborview this winter

Elsewhere on the waterfront, the homeport is one of the few projects still on schedule. Several nearby projects have been pushed back or dropped.

  • Lift Station 5, 2800 block of Harborview Drive. The nearly 50-year-old sewer station on the shoreline is being moved upslope. Slip-lining of the gravity main was set to begin Oct. 26 and take five or six business days. Affected homeowners get at least a week's notice before they need to limit sewer use, and construction pauses before the December holidays.
  • Skansie Park Welcome Plaza splash pad. Council rejected all bids on Aug. 10 and postponed the replumbing and rewiring to 2027. The city planned to rebid on Oct. 13 for an early 2027 start.
  • Harborview Drive pavement. Repaving and ADA work from Ancich Park to Pioneer Way had been added to a citywide paving project in February. City staff later removed the Harborview segment "due to project cost and public impacts."

The holiday calendar falls around all of this. The Downtown Waterfront Alliance's Shop the Harbor launch runs Saturday, Nov. 14, from noon to 8 p.m. The Harbor History Museum hosts Light the Night: St. Lucia Festival on Friday, Dec. 4, from 5:30 to 7:30 p.m. Gig Harbor Now's 2026 calendar puts the Christmas tree lighting at Skansie Brothers Park on Dec. 5 and the Lighted Boat Parade on Dec. 12. The Gig Harbor Yacht Club's listing gives Dec. 12 from 5 to 7 p.m. in one spot and Dec. 13 in another, so check the club's page before you claim a spot on the water.

When the boats go by on parade night, crews will still have work ahead in the water off Ancich Waterfront Park. The fish-window deadline is Feb. 15, 2027, and the new floats are scheduled to be in by then.

If you're watching the south shore and wondering how a working dock could change your walk, your view or a home along Harborview, I'm glad to talk it through. Catt Johnson keeps close tabs on waterfront projects like this one. Book a Call and we'll look at what the homeport means for your stretch of the harbor.